901.06 – Final Building Specifications
The architect shall proceed with the preparation of the final working drawings, specifications, and contract documents after receiving authorization from the Board of Directors.
The Superintendent, staff, and Board shall continue to provide information and decisions necessary for the architect to finalize the plans.
It shall be the responsibility of the architect to obtain approval of the final plans by the Superintendent, State Fire Marshal, Local Building Authorities, and the Board of Directors before releasing the plans for bid purposes.
Date of Adoption: July 1, 1985
Legal Reference: (Code of Iowa) Chapter 297.7
Reviewed & Revised: September 3, 1991; August 1, 1994; May 4, 1998; February 7, 2005; February 1, 2010; December 19, 2016