In November 2019, our communities overwhelmingly passed a bond issue to build a new stadium, a new gymnasium addition, and to make improvements to all of our facilities. We will update this page with new information, pictures, and estimated timelines of completion. |
STADIUM
Contractor – Graphite, Inc.
Contracted completion – July 2021
Current expected completion – November 2021
GYMNASIUM
Contractor – Graphite, Inc.
Contracted completion – July 2022
Current expected completion – October 2022
SAFE/SECURE ENTRIES
Contractor – TBB&M
Contracted completion – Aug 13, 2021
Current expected completion – Aug 13, 2021 *front door entry doors on backorder until September*
ELEMENTARY RESTROOOM UPDATES
Contractor – TBB&M
Contracted completion – Aug 13, 2021
Current expected completion – Aug 13, 2021
MINGO SITE DEMO
Contractor – PCI
Contracted completion – May, 2021
Completed – May, 2021 *due to demo damage, a portion of the hallway restrooms attached to the gym must be fixed. Currently planned to be completed in November.
SOFTBALL FIELD LIGHTS
Contractor – VanMaanen Electric Inc.
Contracted completion – May 7, 2021
Completed – May 7, 2021
BASEBALL RIGHT FIELD IMPROVEMENT
Contractor – Graphite, Inc.
Contracted completion – November 2020
Completed – May 2021