In November 2019, our communities overwhelmingly passed a bond issue to build a new stadium, a new gymnasium addition, and to make improvements to all of our facilities.  We will update this page with new information, pictures, and estimated timelines of completion.

 

STADIUM

Contractor – Graphite, Inc.

Contracted completion – July 2021

Current expected completion – November 2021

GYMNASIUM

Contractor – Graphite, Inc.

Contracted completion – July 2022

Current expected completion – October 2022

SAFE/SECURE ENTRIES

Contractor – TBB&M

Contracted completion – Aug 13, 2021

Current expected completion – Aug 13, 2021 *front door entry doors on backorder until September*

ELEMENTARY RESTROOOM UPDATES

Contractor – TBB&M

Contracted completion – Aug 13, 2021

Current expected completion – Aug 13, 2021

MINGO SITE DEMO

Contractor – PCI

Contracted completion – May, 2021

Completed – May, 2021 *due to demo damage, a portion of the hallway restrooms attached to the gym must be fixed.  Currently planned to be completed in November.

SOFTBALL FIELD LIGHTS

Contractor – VanMaanen Electric Inc.

Contracted completion – May 7, 2021

Completed – May 7, 2021

BASEBALL RIGHT FIELD IMPROVEMENT

Contractor – Graphite, Inc.

Contracted completion – November 2020

Completed – May 2021